Zabol Water Treatment Plant Project

Subject of the Contract:
Procurement, transportation, installation, and commissioning of the remaining facilities of the water treatment plant in Sistan’s cities


Employer: Sistan and Baluchestan Water and Wastewater Company
Consultant: Toossab Consulting Engineers Company
Contractor: Saabniroo
Duration of Contract: 20 months
Project location: Sistan and Baluchestan Province - Zabol City



Project Description:
- Procurement, transportation, testing, and commissioning of the water treatment plant installations with a capacity of 2050 liters per second.
- Construction of various parts of the treatment plant, including the input screen, ozonation, chlorination, the plant’s output waterscape, output pumping station, and chemical building.
- Construction of the necessary facilities to get water from basin No. 3 with a debit of 16,000 cubic meters per hour.